Plumbing Control Application Form Fees

2023 CONTROL FORM FEES      

Installation Control Application Form

(1ɸ-3ɸ) Transient Current

150 TL

1ɸ 63A

200 TL

3ɸ 63A

700 TL

3ɸ 80A

950 TL

3ɸ 100A (Included) - up to 159A

 

1.400 TL

3ɸ 160A (Included) - up to 249A

2,000 TL

3ɸ 250A (Included) - up to 399A

2.500 TL

3ɸ 400A (Included) - up to 629A

6,000 TL

3ɸ 630A (Included) - up to 999A

12,000 TL

3ɸ 1000A and ABOVE

25,000 TL

 

Solar Energy Systems Installation Control Application Form

 

Amount of Installed Power

Fee

Up to 5 kWp  (Including 5kWp)

350 TL

Between 5-10 kWp (Including 10kWp)

500 TL

Between 10 kWp and 50 kWp

(Including 50 kWp)

To 10 kWp  additional=500 TL (+)

30 TL for each kWp

51 kWp and ABOVE

To 50 kWp  additional=1.700 TL (+)

40 TL for each kWp

 

* Fees valid as of 01/11/2023.

 

Contact Us

Address: Organize Sanayi Bölgesi 20. Sokak No:11 Nicosia / NORTH CYPRUS

Phone: +90 (392) 225 23 73

Phone: +90 (392) 366 40 17

Email: [email protected]